The works on dismantling of the light roof of the Unit 4 turbine hall are being carried out at the site of the New Safe Confinement (NSC).
Sergei Poplygin, Head of Shop for Object Shelter and New Safe Confinement Operation commented on dismantling methods: “The method itself of dismantling, fragmentation and handling of dismantled roof is the following. The panel is dismantled with size of 12x3 meters. Using the crane, it is descended directly into the body of a special motor vehicle. Subsequently, this vehicle moves the panel to the fragmentation site at the territory of the former assembly area of the NSC arch. At this site, the panels are fragmented to allow their transportation in the body of a KrAZ vehicle”.
Then the fragments removed from the roof will be delivered to "Buryakivka" radioactive waste disposal site.