On May 6, the main stage of Spent Nuclear Fuel Dry Storage Facility (ISF-2) integrated testing with use of spent fuel assembly (SFA) dummies started at the ChNPP industrial site.
The testing includes the receiving of a railcar from ISF-1, processing of 9 dummies (namely detaching the lower and upper spent fuel bundles, inserting the dummies into the fuel storage tubes and double-wall shielding canisters (DWC)). The SSE ChNPP personnel participate in the ISF-2 integrated testing while the representatives of the SNRIU and the SSTC NRS witness this testing.
The completed individual testing of the majority of systems, namely main process systems for handling a transfer cask, SFAs, fuel storage tubes, DWCs etc. enabled to carry out this stage of testing.
From May 18, within the framework of ISF-2 integrated testing with dummies it is scheduled to carry out the primary procedure qualification of welding technique which will be used for DWC handling.