On July 29, a contract was singed for civil works related to New Safe Confinement facility (NSC). Commissioning Stage 2 (CS-2). Dismantling the unstable structures of the SSE ChNPP Shelter in terms of “early” dismantling. The signatories are the SSE Chornobyl NPP and Ukrbudmontazh who became an awardee as the result of auction held at Prozorro platform.
In November 2016, New Safe Confinement covered Shelter facility – one of the most powerful symbols of Chornobyl NPP. The surveys and expert evaluations, held within the whole period of Shelter existence, have revealed the structures the probability of whose collapse is very high. Following the stabilization actions taken in 2008 the maximum end-of-service-life deadline of the stabilized structures was specified as late 2023.
As per Shelter Implementation Plan the dismantling of these unstable building structures (so called early dismantling) is to be commenced following the NSC takeover for operation and to be completed by the end of 2023.